Trails Project Schedule Update – December 20, 2024
MUD 365 has completed its inspection of drainage infrastructure underneath the trails. While they did identify some necessary maintenance and repairs, MUD 364 does believe those efforts will not impact the trails themselves. We’ve therefore made the decision to proceed with Phases 2 and 3 of our Trail Project without any further delays. The updated general schedule for each phase is detailed below. Please remember that this schedule is tentative and subject to change.
- Phase 1 (Cypress Hall Drive to Coles Crossing Drive): currently underway and expected to be complete by mid-January
- Phase 2 (Tylermont Drive to Coles Crossing Drive): January 15 – March 11
- Phase 3 (Coles Crossing Drive to Latticevine Drive): March 12 – May 16
We are updating this page regularly. Please check back for the latest on the project.