The Board has heard the community’s frustration with the progress of the Trail Improvement Project and provides the following update on the project schedule:
- The trail rehabilitation project was originally intended to start over the summer. Unfortunately, we were unable to get the necessary permissions to begin work until the fall.
- The sidewalk along Coles Crossing Drive (near Bowden Creek Drive) will be poured and reopened within the next week. The Board hopes this will alleviate pedestrian traffic to/from Sampson Elementary.
- Before the trail was demolished, we had to make assumptions about the conditions of the ground beneath the trail. Our schedule and the subsequent trail closure was based on those assumptions. Once the contractor removed the existing trail, they discovered unforeseen conditions that required further testing and potential modifications to the construction of the new trail. This testing is nearly complete. The District’s landscape architect expects to receive the information they need within the next week to determine if any changes are necessary.
- Simultaneous with the start of MUD 364’s trail project, MUD 365 discovered that critical drainage infrastructure underneath the trails needs to be repaired and potentially replaced. To avoid costly repairs to newly poured trails, we have been forced to stop work on the trails while we determine the extent of the drainage repairs. MUD 364 is coordinating with MUD 365 to align the schedule for the drainage repair work with the remainder of MUD 364’s trail project.
While the Board understands the community’s frustration on the lengthy trail closure, please know that we continue to press the trail project contractor to work swiftly and are committed to keeping the community informed on the progress and timeline going forward.
Please refer back to this page for future updates on the project and timeline for reopening the trails. The Board will provide an updated general schedule for each phase in the next update.