About Harris County MUD 364

This author has not yet filled in any details.
So far Harris County MUD 364 has created 63 blog entries.

Update on Sanitary Sewer Repair Project – Lane Closure on Coles Crossing Dr.

The contractor performing the sanitary sewer repair project continues its work in the Coles Crossing neighborhood. Earlier this week, 3 trees along Coles Crossing Drive near Bowden Creek were removed. The trees sat directly above the sewer lines and had to be removed to perform the repairs.

The contractor is expected to begin work at the corner of Bowden Creek Drive and Coles Crossing Drive on the week of June 8th. The work in this area will take approximately 4 days, weather permitting. Unfortunately, one lane will be closed during this time as equipment and personnel will be staged on the street. Completion and restoration of the area, replacement of sidewalk and other remediation requirements will take longer. The contractor has not yet provided a detailed schedule, but the District is confident they will work as quickly and safely as possible.

Please beware of your surroundings and drive slowly and cautiously through the work zone.

Thank you in advance for your understanding.

By |2025-09-01T15:17:56-05:00May 9th, 2025|Archive|

MUD 364 Sanitary Sewer Repairs & Tree Removal

Over the past few months, Mud 364 contractors have been examining the sanitary sewer system within the District. These inspections identified some areas that require repairs.

Removal and replacement of some sections of the sanitary sewer system will begin this week. Unfortunately there are 3 trees along Coles Crossing Drive near Bowden Creek that sit directly above the sewer lines. These trees must be removed to facilitate the repairs. We will be replanting vegetation and trees in more suitable locations to prevent a similar situation in the future. Planting will begin in the cooler fall to give new trees and vegetation the best opportunity to thrive.

While we always strive to protect the community’s trees, please understand that these are necessary repairs to ensure the sustainability of our sewer infrastructure.

Thank you in advance for your understanding.

By |2025-09-01T15:18:25-05:00May 6th, 2025|Archive|

Sanitary Sewer System Repair Notice

MUD 364 is conducting an underground sewer televising project throughout the District. The results from Sections 9 and 10 identified some issues that need to be addressed, including areas where the lines are sagging and are not fully transporting waste products to the sanitary lift station and on to the sewer treatment plant.

To ensure the ongoing reliability of our sewer infrastructure, MUD 364 has opted to begin those repairs. This project will require excavation of some sidewalks and driveways. Over the next few weeks, the District and the Contractor will provide residents with notice of when the excavation work will begin. Residents directly impacted by the removal of a driveway or sidewalk will also be notified by certified mail.

The Contractor is required to provide notice 24 – 48 hours before beginning work on or adjacent to your property. The work will not require residents to be home and at no time will field crews enter your home. Any pavement, grass, fencing, trees, landscaping, or sprinklers that are damaged during construction will be restored by the Contractor at no cost to the resident.

The Board of Directors of MUD 364 is committed to providing every residence with superior water and sewer infrastructure and we appreciate your patience as we make these necessary repairs.

Questions?
If you have any questions about the project, please contact our engineer.

Mark Cervantes, P.E.
Volger & Spencer Engineering, LLC
713-782-0042

By |2025-09-01T15:18:31-05:00April 22nd, 2025|Archive|

Phase 3 Remains Closed to Public – Please Stay Out of Fenced Areas!

Phase 3 of the Trail Project (“T-Loop”) remains closed to the public as our trail contractor completes its work on the final phase.

Earlier this week, the trail contractor poured the concrete in Phase 3 and secured the area with clearly marked fences. Unfortunately, individuals ignored the fences and damaged the freshly poured concrete, as shown in the pictures below. The District is exploring all its options to fix this issue but there will likely be increased project costs and delays.

The Board urges all residents to keep out of fenced areas even if it looks like there is no active work in progress.

In the meantime, please visit Phases 1 and 2 of the trail system!

By |2025-09-01T15:18:13-05:00April 3rd, 2025|Archive|

UPDATED NOTICE – Sanitary Sewer Cleaning and Televising Project – Sections 14 – 17, 20 & 21

Earlier this week, HCMUD 364 began cleaning and inspecting the sanitary sewer system in Coles Crossing, Sections 14 – 17, 20 & 21. This is a continuation of the cleaning and televising performed in Sections 9 & 10 last year.

Doorhangers will be distributed to homes in the affected areas prior to the start of the project in each respective section. If a sewer manhole is located on your property, contractors may need to gain access to your property. Your cooperation is appreciated.

The estimated timeline of when the contractor will begin working within each section is provided below. Please note this is a general timeline and subject to change. The contractor for this project is CleanView Resources LLC.

  • March 17 – March 19 – Section 16
  • March 19 – begin Section 20
  • March 21 – begin Section 14
  • March 24 – begin Sections 17 & 15

If any problems with your sewer service occur during the work, please contact the District’s Operator, Municipal Operations & Consulting, at 281-367-5511.

If you have any other questions about this project, please contact the District’s Engineer, Mr. Mark S. Cervantes, P.E. with Vogler & Spencer Engineering, Inc. at 713-782-0042.

By |2025-09-01T15:19:09-05:00March 19th, 2025|Archive|

Sanitary Sewer Cleaning and Televising Project – Sections 14 – 17, 20 & 21

HCMUD 364 will begin cleaning and inspecting the sanitary sewer system in Coles Crossing, Sections 14 – 17, 20 & 21. This is a continuation of the cleaning and televising performed in Sections 9 & 10 last year.

Doorhangers will be distributed to homes in the affected areas prior to the start of the project. If a sewer manhole is located on your property, contractors may need to gain access to your property. Your cooperation is appreciated.

The project is expected to begin on or around Monday, March 17 and will continue through the beginning of June. The contractor for this project is CleanView Resources LLC.
If any problems with your sewer service occur during the work, please contact the District’s Operator, Municipal Operations & Consulting, at 281-367-5511.

If you have any other questions about this project, please contact the District’s Engineer, Mr. Mark S. Cervantes, P.E. with Vogler & Spencer Engineering, Inc. at 713-782-0042.

By |2025-03-20T15:25:48-05:00March 17th, 2025|Archive|

MUD 364 Trail Update – Phase 2 is OPEN!

Phase 2 of the new trails is now open for pedestrian traffic. Phase 2 is located from Tylermont Drive to Coles Crossing Drive by the lap pool.

Phase 1 of the trail system opened in Mid-January. Phase 1 is located from Cypress Hall Drive to Coles Crossing Drive.

There are site furnishings to be added including benches, garbage cans, drinking fountains and dog/pet waste stations. These are being installed upon receipt from the manufacturers. Landscaping and new signage will follow at a later date.

As the trails open, please remember to pick up after your pets. E-coli bacteria from pet waste is the number 1 contributor to Cypress Creek contamination. A clean Cypress Creek benefits us all.

Thank you for your patience as we strive to deliver a quality and lasting trail system.

By |2025-09-01T15:19:35-05:00March 12th, 2025|Trails Project|

Phases 2 and 3 Remain Closed to Public – Please Stay Out of Fenced Areas

Phases 2 and 3 of the Trail Project (main loop and “T-Loop”) remain closed to the public. For your safety, please keep out of all fenced areas and refrain from moving or bypassing construction fences and orange construction barricades/barrels. While work may not be actively in progress, the fenced area is part of the project site and residents must stay out of the area for their safety and the safety of our contractors. Continued public interference could cause costly project delays.

In the meantime, we encourage you to visit Phase 1 of the Trail Project which was completed in mid-January!

By |2025-09-01T15:18:42-05:00February 6th, 2025|Archive|

Phase 2 is Underway!

Our trail contractor has started work on Phase 2 of the trail project.  The initial framing is well underway and 700 feet of fresh concrete was poured today.  We currently anticipate Phase 2 to open in late March, weather permitting.
The recent rains have slowed progress slightly, but we still expect the project to be completed in full by early June.  Watch for another update in mid-February.
By |2025-09-01T15:18:50-05:00January 31st, 2025|Archive|
Go to Top