Loading...
Latest News Archives2023-04-05T16:43:38-05:00

Latest News Archives

Update on Sanitary Sewer Repair Project – Lane Closure on Coles Crossing Dr.

The contractor performing the sanitary sewer repair project continues its work in the Coles Crossing neighborhood. Earlier this week, 3 trees along Coles Crossing Drive near Bowden Creek were removed. The trees sat directly above the sewer lines and had to be removed to perform the repairs.

The contractor is expected to begin work at the corner of Bowden Creek Drive and Coles Crossing Drive on the week of June 8th. The work in this area will take approximately 4 days, weather permitting. Unfortunately, one lane will be closed during this time as equipment and personnel will be staged on the street. Completion and restoration of the area, replacement of sidewalk and other remediation requirements will take longer. The contractor has not yet provided a detailed schedule, but the District is confident they will work as quickly and safely as possible.

Please beware of your surroundings and drive slowly and cautiously through the work zone.

Thank you in advance for your understanding.

By |May 9th, 2025|

MUD 364 Sanitary Sewer Repairs & Tree Removal

Over the past few months, Mud 364 contractors have been examining the sanitary sewer system within the District. These inspections identified some areas that require repairs.

Removal and replacement of some sections of the sanitary sewer system will begin this week. Unfortunately there are 3 trees along Coles Crossing Drive near Bowden Creek that sit directly above the sewer lines. These trees must be removed to facilitate the repairs. We will be replanting vegetation and trees in more suitable locations to prevent a similar situation in the future. Planting will begin in the cooler fall to give new trees and vegetation the best opportunity to thrive.

While we always strive to protect the community’s trees, please understand that these are necessary repairs to ensure the sustainability of our sewer infrastructure.

Thank you in advance for your understanding.

By |May 6th, 2025|

Sanitary Sewer System Repair Notice

MUD 364 is conducting an underground sewer televising project throughout the District. The results from Sections 9 and 10 identified some issues that need to be addressed, including areas where the lines are sagging and are not fully transporting waste products to the sanitary lift station and on to the sewer treatment plant.

To ensure the ongoing reliability of our sewer infrastructure, MUD 364 has opted to begin those repairs. This project will require excavation of some sidewalks and driveways. Over the next few weeks, the District and the Contractor will provide residents with notice of when the excavation work will begin. Residents directly impacted by the removal of a driveway or sidewalk will also be notified by certified mail.

The Contractor is required to provide notice 24 – 48 hours before beginning work on or adjacent to your property. The work will not require residents to be home and at no time will field crews enter your home. Any pavement, grass, fencing, trees, landscaping, or sprinklers that are damaged during construction will be restored by the Contractor at no cost to the resident.

The Board of Directors of MUD 364 is committed to providing every residence with superior water and sewer infrastructure and we appreciate your patience as we make these necessary repairs.

Questions?
If you have any questions about the project, please contact our engineer.

Mark Cervantes, P.E.
Volger & Spencer Engineering, LLC
713-782-0042

By |April 22nd, 2025|

Go to Top