We appreciate the community’s patience as the contractor performing the sanitary sewer system repairs in sections 9 and 10 has been delayed over the last month.
The contractor expects to begin work at the corner of Bowden Creek Drive and Coles Crossing Drive on Monday, June 23, weather permitting. The work in this area will take approximately 4 days. Unfortunately, one lane will be closed during this time as equipment and personnel will be staged on the street.
Please be aware of your surroundings and follow directions of flagman directing traffic through the work zone.
Thank you in advance for your understanding.