Trail Beautification Project Set to Begin
The Trail Beautification Project is set to begin on Monday, September 16th, 2024. For more information check the Trail Projects Page.
Trails Project
The Board of Directors is excited to announce the start of the District’s Trail Improvements Project!
The project will begin on September 16, 2024 and is anticipated to last about 6-months, pending any weather or unanticipated delays.
Demolition of the current trail will be done in three phases. The general schedule for each phase is detailed below; these dates are tentative and subject to change. The District will provide updates to the schedule when they become available.
- Phase 1 (trail between Cypress Hall Drive and Coles Crossing Drive): September 28 – November 9
- Phase 2 (trail between Tylermont Drive and Monteigne Lane): October 7 – December 23
- Phase 3 (trail between Coles Crossing Drive and Latticevine Drive): October 26 – February 6
Please note that while demolition of the current trail will be completed in phases, the entire MUD 364 trail system will be closed until all phases are complete. FOR YOUR SAFETY, PLEASE DO NOT ACCESS THE TRAIL OR ANY CONSTRUCTION AREA UNTIL THE entire project is complete.
The District will provide periodic updates on this webpage and via text alerts.