Sunset Plaza – New Trail Amenities Coming Soon!
We’re excited to announce the next phase of the Trail Improvements Project will begin soon!
Construction Start: week of November 17, 2025
Estimated Duration: approximately three weeks (weather permitting)
The new Sunset Plaza will be located along the trail, just south of the Coles Crossing Swim Center. This next phase will add comfortable benches, colorful landscaping and fresh trees – the perfect place to pause and enjoy the trails you love!
At this time, we expect the trails to remain open during construction. We urge the public to observe all warning signs and barricades until the project is complete for your safety and the safety of construction crews.
We’ll share regular updates here and through text alerts as work progresses.
Thanks for your patience and excitement as we continue to improve our community trails!

MUD 364 Trail Update – Phase 2 is OPEN!
Phase 2 of the new trails is now open for pedestrian traffic. Phase 2 is located from Tylermont Drive to Coles Crossing Drive by the lap pool.
Phase 1 of the trail system opened in Mid-January. Phase 1 is located from Cypress Hall Drive to Coles Crossing Drive.
There are site furnishings to be added including benches, garbage cans, drinking fountains and dog/pet waste stations. These are being installed upon receipt from the manufacturers. Landscaping and new signage will follow at a later date.
As the trails open, please remember to pick up after your pets. E-coli bacteria from pet waste is the number 1 contributor to Cypress Creek contamination. A clean Cypress Creek benefits us all.
Thank you for your patience as we strive to deliver a quality and lasting trail system.

Trails Project Schedule Update – December 20, 2024
MUD 365 has completed its inspection of drainage infrastructure underneath the trails. While they did identify some necessary maintenance and repairs, MUD 364 does believe those efforts will not impact the trails themselves. We’ve therefore made the decision to proceed with Phases 2 and 3 of our Trail Project without any further delays. The updated general schedule for each phase is detailed below. Please remember that this schedule is tentative and subject to change.
- Phase 1 (Cypress Hall Drive to Coles Crossing Drive): currently underway and expected to be complete by mid-January
- Phase 2 (Tylermont Drive to Coles Crossing Drive): January 15 – March 11
- Phase 3 (Coles Crossing Drive to Latticevine Drive): March 12 – May 16
We are updating this page regularly. Please check back for the latest on the project.
Trail Update- December 13th, 2024
The contractor is progressing swiftly with construction of Phase 1 of the Trail Project! We anticipate the contractor will begin pouring concrete on the sections of Phase 1 that connect to Coles Crossing Drive the week of December 16. The contractor will then pour the sections that connect to Cypress Hall Drive the week of December 23 and the first week of 2025. This preliminary schedule is subject to change due to weather conditions. Check back here for future updates.
Trails Project Update – December 4, 2024
Construction of the Trail Project will start up again soon! The contractor will begin working on forming the Phase 1 trail within the next week and will begin pouring the concrete shortly thereafter. We anticipate Phase 1 will be completed in 4 to 5 weeks, weather permitting.
We are waiting for information on what, if any, repairs are needed to drainage infrastructure underneath the trails in Phases 2 and 3. At this time, we do not know how long Phases 2 and 3 will be delayed but are working diligently to keep the project moving forward. We hope to be able to have the information we need to make a decision on how to proceed in the next few weeks.
Continue to check back here for periodic updates.
Trails Project
The Board of Directors is excited to announce the start of the District’s Trail Improvements Project!
The project will begin on September 16, 2024 and is anticipated to last about 6-months, pending any weather or unanticipated delays.
Demolition of the current trail will be done in three phases. The general schedule for each phase is detailed below; these dates are tentative and subject to change. The District will provide updates to the schedule when they become available.
- Phase 1 (trail between Cypress Hall Drive and Coles Crossing Drive): September 28 – November 9
- Phase 2 (trail between Tylermont Drive and Monteigne Lane): October 7 – December 23
- Phase 3 (trail between Coles Crossing Drive and Latticevine Drive): October 26 – February 6
Please note that while demolition of the current trail will be completed in phases, the entire MUD 364 trail system will be closed until all phases are complete. FOR YOUR SAFETY, PLEASE DO NOT ACCESS THE TRAIL OR ANY CONSTRUCTION AREA UNTIL THE entire project is complete.
The District will provide periodic updates on this webpage and via text alerts.